PROJECTS IN ZUNYI, CHINA —
Last Updated December 31, 2007
North
Gaojiu Rd. Huichuan District, Zunyi City
1,023
New Occupancy: 850, as of Dec. 31, 2007
Previous Occupancy: 828, as of Oct. 30, 2007
Previous Occupancy: 825, as of Aug 4, 2007
Previous Occupancy: 820, as of March 19, 2007
New LPG Service & Percentage: 555, Approx. 65.3% (as of Dec. 31, 2007)
Previous LPG Service & Percentage: 540, Approx. 52.78% (as of Mar. 19, 2007)
Center
supplying depot (bottles room, equipment room, duty room) underground
pipeline network, pipeline indoors throughout the buildings,
controlling valves & meters.
October
10, 2002
Project 1 Photos
|
South
Gaojiu Rd. Huichuan District, Zunyi City
578
New Occupancy: 375 (as of Dec. 31, 2007)
Previous Occupancy: 370 (as of Oct. 30, 2007)
Previous Occupancy: 265 (as of Mar. 19, 2007)
New LPG Service & Percentage: 188, Approx. 50% (as of Dec. 31, 2007)
Previous LPG Service & Percentage: 185, Approx. 50% (as of Oct. 30, 2007)
Previous LPG Service & Percentage: 180, Approx. 31.14% (as of Mar. 19, 2007)
Description: Center
supplying depot (bottles room, equipment room, duty room) underground
pipeline network, pipeline indoors throughout the buildings,
controlling valves & meters.
Completion Date: December
30, 2004
Project 2 Photos
|
Location: Middle
of Gaojiu Rd. Huichuan District, Zunyi City
Number of Residents: 42
New Occupancy: 5 as (of Dec. 31, 2007)
Previous Occupancy: 5 as (of Oct. 30, 2007)
Previous Occupancy: 3 (as of Mar. 19, 2007)
New LPG Service & Percentage: 2, Approx. 40% (as of Dec. 31, 2007)
Previous LPG Service & Percentage: 2, Approx. 40% (as of Oct. 30, 2007)
Previous LPG Service & Percentage: 2, Approx. 4.76% (as of Mar. 19, 2007)
Description: Underground
pipeline network, pipeline indoors threw-out the buildings,
controlling valves & meters. This project is for Zunyi
Medical University.
Majority of the homeowners are working in the University.
Completion Date: July
1, 2005
|
(Pending)
Location: Middle
of Gaojiu Rd. Huichuan District, Zunyi City
Number of Residents: 60
Occupancy: 0
LPG Service & Percentage: 0, Approx. 0%
Description: TBD
Completion Date: TBD
|

Location: Guangzhou
Rd. Huichuan District, Zunyi City
Number of Residents: 1,067
(994 completed + 73 uncompleted)
New Occupancy: 801 (as of Dec. 31, 2007)
Previous Occupancy: 489 (as of Oct. 30, 2007)
Previous Occupancy: 162 (as of Mar. 19, 2007)
New LPG Service & Percentage: 367, Approx. 45.8% (as of Dec. 31, 2007)
Previous LPG Service & Percentage: 290, Approx. 59.3% (as of Oct. 30, 2007)
Previous LPG Service & Percentage: 138,
Approx. 12.83% (as of Mar. 19, 2007)
Description: Center
supplying depot (bottles room, equipment room, duty room) underground
pipeline network, pipeline indoors threw-out the buildings,
controlling valves & meters. Pipeline Number 5 will serve 1,067 condominiums and the original plan was to build 16 buildings, housing 1,067 residences. 15 buildings containing 994 residences were completed in December, 2005. The developer is awaiting government approval to proceed with the 16th building of 73 residences.
Completion Date: December
28, 2005
|
Location: Taoxi
Rd. Honghuagang District, Zunyi City
Number of Residents: 5,000
Occupancy: 0
LPG Service & Percentage: 0,
Approx. 0%
Description:
Completion Date: TBD
|

Location: Middle
of Gaojiu Rd. Huichuan District, Zunyi City
Number of Residents: 74
New Occupancy: 25 (as of Dec. 31, 2007)
Previous Occupancy: 21 (as of Oct. 30, 2007)
Previous Occupancy: 5 (as of Mar. 19, 2007)
New LPG Service & Percentage: 22, Approx. 88% (as of Dec. 31, 2007)
Previous LPG Service & Percentage: 14, Approx. 66.6% (as of Oct. 30, 2007)
Previous LPG Service & Percentage: 2,
Approx. 2.70% (as of Mar. 19, 2007)
Description: Sharing Project 2 center supplying depot (bottles room, equipment room, duty room) underground pipeline network, pipeline indoors throughout the buildings, controlling valves & meters.
Completion Date: October
28, 2006
|

Location: Minsheng
Residence Area: Building A & Building C, Zunyi City
Number of Residents: 242
Occupancy: 0
LPG Service & Percentage: 0, Approx. 0%
Description: This project is deferred for the capital problem of Party A.
Completion Date: TBD
|

Location: Zunyi
Tobacco Company Ltd, Zunyi City
Number of Residents: 150
Occupancy: 0
LPG Service & Percentage: 0, Approx. 0%
Description: This project started in October
Completion Date: Est. December, 2007 — It is delayed by the slowing of construction of the buildings.
|

Location: Zunyi Yongcheng Real Estate Co., Ltd.
Number of Residents: 1000
Occupancy: 0
LPG Service & Percentage: 0, Approx. 0%
Description: This project will start next year
Completion Date: TBD |

Location: Zunyi City Yong-sheng Real Estate Development Co. Ltd.
Number of Residents: Approx. 192
Occupancy: 0
Number for LPG Service & Percentage: 0, Approx. 0%
Description: This project will begin in early 2008
Completion Date: Est. June, 2008 |
|
|